UNDP risk management measures during grant formulation  

A number of standard and key controls should be established in the key phases of project formulation and implementation to ensure a mitigation of some of the most common risks faced by UNDP-implemented Global Fund projects, as listed in the Risk Catalogue for Global Fund projects. Some key risk management considerations to embed in the formulation of the grant are listed below.  

Risk Assessment during key start-up activities: when notified that UNDP is being considered as Principal Recipient (PR), the UNDP Country Office with support from the Regional Bureau and the BPPS GFPHST, should conduct an assessment of the risks in taking the PR role to inform the decision to accept the role and the formulation of the transition and grant making work plan. See Principal Recipient Start-up section of this Manual. 

Project quality assurance and appraisal – UNDP POPP (Programme and Project Management (PPM) Appraise and Approve) requires the appraisal of the quality of every project before finalisation. This is done via a Project Quality Assurance assessment of the project by the Project Assurance function in the Country Office (CO) and a Local Project Appraisal meeting. In this regard, during the formulation of Global Fund-funded projects, ensure: 

  • The CO programme team (as Project Assurance) is involved in the quality review of the project during the grant formulation phase. If UNDP is not assigned as PR during the funding request, consider involving the CO programme team as soon as possible during the negotiation of the project. 
  • UNDP’s Quality Standards for Programming are reflected in the formulation of the funding request, the negotiation of the grant (if UNDP is not assigned as PR during the funding request stage) and the UNDP project document. 
  • It is recommended to ensure a UNDP’s preliminary feedback to the draft funding request is collected and integrated in the funding request / project as soon as possible. This feedback includes programming quality, security, health procurement and supply management, oversight, financial management, human resources, and monitoring and evaluation considerations from the UNDP CO, BPPS Global Fund Partnership and Health Systems Team (GFPHST).  If the project has been classified as a ‘high-risk project’ by the Regional Bureau/BPPS, also include Regional Bureau’s feedback. 

Construction – The UNDP Construction Works policy and the PPM Appraise and Approve policy foresee the delegation for construction works by the Regional Bureau to the Resident Representative (RR) before project approval. Ensure this is obtained before the finalisation of the project.



Resources

Functional Area: Risk Management      Project Stage: Grant Making and Signing      Author: UNDP      Language: English      Type: Policies, Procedures and guidance      Topic: UNDP risk management measures during grant formulation , AML / CFT operational guidance      Resource File Format: Link      Resource Accessibility: Publicly accessible